Plumbing
Fix complete WC and wash-hand basin set
Fix client-supplied WC and wash-hand basin set to prepared points, including normal connection and testing labour. Major pipe rerouting excluded.
Methodology
Workmanship benchmark only; pan connectors, traps, flexible connectors and specialist accessories should be added where not client supplied.
Source basis
2-bedroom M&E labour BOQ guide.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 set of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 set | Resource unit | Qty / 1 set | Unit price | Cost / set |
|---|---|---|---|---|---|---|
| Minor fixing / sealant consumables | Consumable | 1 | set | 1 | ₦1,500 | ₦1,500 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 set | Resource unit | Qty / 1 set | Unit price | Cost / set |
|---|---|---|---|---|---|---|
| Plumber fixing labour | Labour | 1 | set | 1 | ₦15,000 | ₦15,000 |
Personal rate calculator
Change quantities, prices and allowances
Cost additions