Plumbing
Fix shower set and control
Fix client-supplied shower head/rail and control to prepared plumbing points.
Methodology
Concealed-body installation before tiling is a different activity and should be priced separately.
Source basis
2-bedroom M&E labour BOQ guide.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 No. of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 No. | Resource unit | Qty / 1 No. | Unit price | Cost / No. |
|---|---|---|---|---|---|---|
| Minor connectors / sealant | Consumable | 1 | No. | 1 | ₦750 | ₦750 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 No. | Resource unit | Qty / 1 No. | Unit price | Cost / No. |
|---|---|---|---|---|---|---|
| Plumber fixing labour | Labour | 1 | No. | 1 | ₦5,000 | ₦5,000 |
Personal rate calculator
Change quantities, prices and allowances
Cost additions