Earthworks
Sharp sand filling / blinding
Sharp sand supplied, spread to required level and lightly compacted.
Methodology
Allows 10% for loose-to-placed quantity. Delivery basis should be changed to the actual site market.
Source basis
Residential BOQ and FMC aggregate benchmark.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 m³ of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 m³ | Resource unit | Qty / 1 m³ | Unit price | Cost / m³ |
|---|---|---|---|---|---|---|
| Sharp sand incl. 10% allowance | Material | 1.1 | m³ | 1.1 | ₦14,400 | ₦15,840 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 m³ | Resource unit | Qty / 1 m³ | Unit price | Cost / m³ |
|---|---|---|---|---|---|---|
| Spreading labour | Labour | 1 | m³ | 1 | ₦1,200 | ₦1,200 |