Formwork
Economical marine-plywood formwork to reinforced concrete staircase
Stair/landing formwork with plywood facing, timber stringers/joists/bracing, 2x6/Peri support allowance, nails, release agent and higher-detail carpentry labour.
Methodology
Stairs attract more cutting, setting-out and striking labour than flat soffits; the labour factor is therefore separately visible and editable.
Source basis
Residential staircase/formwork methodology normalized with current formwork inputs. Sep 2026 Abuja audit checked plywood, timber, H20/Peri and labour market references; structural/shuttering quantities remain to be validated against a formwork layout. User-approved V2 rule: economical/cheap marine board = 3 casting cycles.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 m² of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 m² | Resource unit | Qty / 1 m² | Unit price | Cost / m² |
|---|---|---|---|---|---|---|
| 18 mm economical marine plywood facing — 3 casting cycles4×8 sheet = 2.9768m²; charged over 3 casting cycles. Abuja construction-board working reference ₦27,500/sheet; editable. | Material | 0.112 | sheet | 0.112 | ₦27,500 | ₦3,079 |
| 2x3 framing / riser supports | Material | 0.35 | length | 0.35 | ₦1,300 | ₦455 |
| 2x2 cleats / bracing | Material | 0.3 | length | 0.3 | ₦1,000 | ₦300 |
| 2x6 stringer / bearer allowance | Material | 0.25 | length | 0.25 | ₦2,500 | ₦625 |
| Peri / H20 support allocationSep 2026 Abuja H20 working purchase reference: ₦16,900; allocation/reuse remains under validation. | Material | 0.04 | No. | 0.04 | ₦16,900 | ₦676 |
| 2–3 inch nails | Consumable | 0.012 | bag | 0.012 | ₦27,000 | ₦324 |
| Release agent / small sundries | Consumable | 1 | m² | 1 | ₦300 | ₦300 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 m² | Resource unit | Qty / 1 m² | Unit price | Cost / m² |
|---|---|---|---|---|---|---|
| Formwork carpenter | Labour | 0.3 | day | 0.3 | ₦15,000 | ₦4,500 |
| Carpenter helper / labourer | Labour | 0.3 | day | 0.3 | ₦8,000 | ₦2,400 |