Formwork
Well-sawn plank formwork to beams and lintels
Traditional beam/lintel shuttering using well-sawn 1x12 plank facing, 2x3 framing, 2x6 bearers, bracing, nails/release agent and erection/striking labour. Plank charged over 4 reuses.
Methodology
Useful where projects use plank below and/or above ground instead of marine plywood. Bearer/support quantity changes with beam size and span.
Source basis
Residential and Jahi formwork evidence. User-approved well-sawn plank reuse: 4 cycles.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 m² of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 m² | Resource unit | Qty / 1 m² | Unit price | Cost / m² |
|---|---|---|---|---|---|---|
| Well-sawn 1x12 plank facing — 4 reuses | Material | 0.2277 | 3.6m length | 0.2277 | ₦3,000 | ₦683 |
| 2x3 side framing | Material | 0.3 | 3.6m length | 0.3 | ₦1,300 | ₦390 |
| 2x6 bottom bearer / strongback | Material | 0.18 | 3.6m length | 0.18 | ₦3,000 | ₦540 |
| 2x2 cleats/bracing | Material | 0.1 | 3.6m length | 0.1 | ₦1,000 | ₦100 |
| Nails | Consumable | 0.008 | bag | 0.008 | ₦27,000 | ₦216 |
| Release agent / ties | Consumable | 1 | m² | 1 | ₦300 | ₦300 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 m² | Resource unit | Qty / 1 m² | Unit price | Cost / m² |
|---|---|---|---|---|---|---|
| Formwork carpenter | Labour | 0.22 | day | 0.22 | ₦15,000 | ₦3,300 |
| Helper | Labour | 0.22 | day | 0.22 | ₦8,000 | ₦1,760 |