Plumbing
Fix kitchen sink and mixer to prepared points
Fix client-supplied sink and mixer to prepared supply/waste points; normal connection and testing included.
Methodology
Cabinet cutting, new pipe routes and specialist traps are excluded unless added by the user.
Source basis
2-bedroom M&E labour BOQ guide.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 No. of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 No. | Resource unit | Qty / 1 No. | Unit price | Cost / No. |
|---|---|---|---|---|---|---|
| Minor connectors / sealant consumables | Consumable | 1 | No. | 1 | ₦1,200 | ₦1,200 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 No. | Resource unit | Qty / 1 No. | Unit price | Cost / No. |
|---|---|---|---|---|---|---|
| Plumber fixing labour | Labour | 1 | No. | 1 | ₦8,000 | ₦8,000 |
Personal rate calculator
Change quantities, prices and allowances
Cost additions