Earthworks
Imported laterite filling, spread and compact
Approved laterite obtained off site, delivered, placed in layers and compacted.
Methodology
Material quantity includes 10% handling/compaction allowance. Haul distance can materially change the rate.
Source basis
FMC/Central Park bulk-material benchmarks; supplier audit still required.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 m³ of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 m³ | Resource unit | Qty / 1 m³ | Unit price | Cost / m³ |
|---|---|---|---|---|---|---|
| Imported laterite incl. 10% allowanceWorking conversion from bulk tipper benchmark. | Material | 1.1 | m³ | 1.1 | ₦8,000 | ₦8,800 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 m³ | Resource unit | Qty / 1 m³ | Unit price | Cost / m³ |
|---|---|---|---|---|---|---|
| Spreading labour | Labour | 1 | m³ | 1 | ₦1,200 | ₦1,200 |
Equipment and movement
Plant & logistics
Plant, hire, fuel, support equipment and logistics are kept separate so they are not hidden inside the material or labour rate.
| Resource | Type | Qty / 1 m³ | Resource unit | Qty / 1 m³ | Unit price | Cost / m³ |
|---|---|---|---|---|---|---|
| Light compaction | Plant | 1 | m³ | 1 | ₦500 | ₦500 |
Personal rate calculator
Change quantities, prices and allowances
Cost additions