Reinforcement
High-yield reinforcement — supply, cut, bend and fix
High-yield reinforcement by theoretical tonne, including 3% cutting/waste, binding/cutting consumables and fixing labour.
Methodology
Lap allowance is not hidden. Add lap separately where measured steel excludes it.
Source basis
Final FMC Keffi reinforcement procurement and fixing basis.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 t of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 t | Resource unit | Qty / 1 t | Unit price | Cost / t |
|---|---|---|---|---|---|---|
| High-yield TMT reinforcement incl. 3% cutting wasteCurrent Abuja observations conflict: bulk tonne checks are lower than some 12m TMT bar quotations when converted using theoretical mass. ₦1.10m/t is retained temporarily until supplier weight/grade is reconciled. | Material | 1.03 | t | 1.03 | ₦1,100,000 | ₦1,133,000 |
| Binding wire / cutting consumables | Consumable | 1 | t | 1 | ₦23,175 | ₦23,175 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 t | Resource unit | Qty / 1 t | Unit price | Cost / t |
|---|---|---|---|---|---|---|
| Cutting, bending and fixing labour | Labour | 1 | t | 1 | ₦85,000 | ₦85,000 |
Personal rate calculator
Change quantities, prices and allowances
Cost additions