Earthworks
Hardcore filling, spread and compact
Hardcore obtained off site, spread to make up levels and compacted in layers.
Methodology
Uses 10% quantity allowance over compacted volume. Material and placing/compaction remain editable separately.
Source basis
FMC final execution model + Central Park material benchmark.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 m³ of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 m³ | Resource unit | Qty / 1 m³ | Unit price | Cost / m³ |
|---|---|---|---|---|---|---|
| Hardcore incl. 10% quantity allowanceWorking conversion from 30t bulk supply. | Material | 1.1 | m³ | 1.1 | ₦22,500 | ₦24,750 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 m³ | Resource unit | Qty / 1 m³ | Unit price | Cost / m³ |
|---|---|---|---|---|---|---|
| Spreading labour | Labour | 1 | m³ | 1 | ₦1,200 | ₦1,200 |
Equipment and movement
Plant & logistics
Plant, hire, fuel, support equipment and logistics are kept separate so they are not hidden inside the material or labour rate.
| Resource | Type | Qty / 1 m³ | Resource unit | Qty / 1 m³ | Unit price | Cost / m³ |
|---|---|---|---|---|---|---|
| Compaction allocation | Plant | 1 | m³ | 1 | ₦500 | ₦500 |
Personal rate calculator
Change quantities, prices and allowances
Cost additions