Ceilings
150 mm grooved POP ceiling-edge detail
30 mm thick × 150 mm wide POP edge detail with repeated longitudinal grooves, including forming/carving, sanding and finishing.
Methodology
Sora guide normalized by provisional 15% O/P removal; material/labour split remains under validation.
Source basis
Sora Restaurant grooved POP guide ₦6,500/lm.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 m of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 m | Resource unit | Qty / 1 m | Unit price | Cost / m |
|---|---|---|---|---|---|---|
| POP/reinforcement/sundry materials | Material | 1 | m | 1 | ₦1,800 | ₦1,800 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 m | Resource unit | Qty / 1 m | Unit price | Cost / m |
|---|---|---|---|---|---|---|
| Forming, carving, sanding and finishing labour | Labour | 1 | m | 1 | ₦3,852 | ₦3,852 |
Personal rate calculator
Change quantities, prices and allowances
Cost additions