Ceilings
Fibre-cement / asbestos-type external ceiling — supply and fix
Supply and fix external ceiling boards to prepared framing including normal cutting, fixings and installation.
Methodology
2-bedroom guide normalized by provisional 15% O/P removal; board type/specification must be updated before verification.
Source basis
2-bedroom Abuja BOQ guide ₦7,500/m².
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 m² of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 m² | Resource unit | Qty / 1 m² | Unit price | Cost / m² |
|---|---|---|---|---|---|---|
| External ceiling board + fixings | Material | 1 | m² | 1 | ₦5,000 | ₦5,000 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 m² | Resource unit | Qty / 1 m² | Unit price | Cost / m² |
|---|---|---|---|---|---|---|
| Installation labour | Labour | 1 | m² | 1 | ₦1,522 | ₦1,522 |
Personal rate calculator
Change quantities, prices and allowances
Cost additions