Finishes
Engineered oak chevron flooring — laying only
Lay employer-supplied engineered oak boards in chevron pattern including detailed setting out, angled cutting, adhesive, edge trims and protection.
Methodology
Chevron productivity is lower than straight layout. Guide rate normalized by stripping a provisional 15% source O/P.
Source basis
Sora Restaurant chevron guide ₦13,500/m².
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 m² of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 m² | Resource unit | Qty / 1 m² | Unit price | Cost / m² |
|---|---|---|---|---|---|---|
| Adhesive, trims, cutting and protection consumables | Material | 1 | m² | 1 | ₦3,000 | ₦3,000 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 m² | Resource unit | Qty / 1 m² | Unit price | Cost / m² |
|---|---|---|---|---|---|---|
| Chevron setting-out and installation labour | Labour | 1 | m² | 1 | ₦8,739 | ₦8,739 |
Personal rate calculator
Change quantities, prices and allowances
Cost additions