Door installation and dressing
Install and dress client-supplied door and frame, including normal fixing consumables and labour.
Methodology
Door type, frame material, hardware and making-good can materially change the rate.
Source basis
2-bedroom labour BOQ guide.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 No. of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 No. | Resource unit | Qty / 1 No. | Unit price | Cost / No. |
|---|---|---|---|---|---|---|
| Fixings / foam / sealant / minor consumables | Consumable | 1 | No. | 1 | ₦2,000 | ₦2,000 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 No. | Resource unit | Qty / 1 No. | Unit price | Cost / No. |
|---|---|---|---|---|---|---|
| Door installation labour | Labour | 1 | No. | 1 | ₦35,000 | ₦35,000 |