Concrete
C15 / nominal 1:3:6 concrete blinding
Nominal 1:3:6 site-mixed plain concrete using 20 mm aggregate; reinforcement and formwork excluded.
Methodology
Uses a 1.54 dry-volume factor and 3% cement batching allowance rather than a fixed historic bags-per-m³ shortcut.
Source basis
Standard nominal-mix build-up aligned to FMC concrete inputs. Sep 2026 audit: cement benchmark updated to Abuja bulk working reference; concrete gang arithmetic corrected.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 m³ of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 m³ | Resource unit | Qty / 1 m³ | Unit price | Cost / m³ |
|---|---|---|---|---|---|---|
| 50 kg cement incl. 3% batching allowance1.54 dry factor for 1:3:6 mix. Sep 2026 Abuja working bulk reference: ₦12,500/50kg bag; editable. | Material | 4.57 | bag | 4.57 | ₦12,500 | ₦57,100 |
| Sharp sand | Material | 0.462 | m³ | 0.462 | ₦14,400 | ₦6,653 |
| Granite / coarse aggregate | Material | 0.924 | m³ | 0.924 | ₦27,000 | ₦24,948 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 m³ | Resource unit | Qty / 1 m³ | Unit price | Cost / m³ |
|---|---|---|---|---|---|---|
| Concrete gang labour1 concrete mason @ ₦15,000/day + 6 labourers @ ₦8,000/day = ₦63,000/gang-day; output basis remains editable. | Labour | 0.125 | gang-day | 0.125 | ₦63,000 | ₦7,875 |
Equipment and movement
Plant & logistics
Plant, hire, fuel, support equipment and logistics are kept separate so they are not hidden inside the material or labour rate.
| Resource | Type | Qty / 1 m³ | Resource unit | Qty / 1 m³ | Unit price | Cost / m³ |
|---|---|---|---|---|---|---|
| Mixer / small plant | Plant | 1 | m³ | 1 | ₦2,769 | ₦2,769 |