Ceilings
Bespoke POP column crown
Bespoke moulded POP crown around top of column including forming, reinforcement/support, sanding and installation.
Methodology
Design-sensitive provisional rate. Source guide normalized by provisional 15% O/P removal.
Source basis
Sora Restaurant column-crown guide ₦25,000/m² pending final architect design.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 m² of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 m² | Resource unit | Qty / 1 m² | Unit price | Cost / m² |
|---|---|---|---|---|---|---|
| POP, reinforcement and moulding materials | Material | 1 | m² | 1 | ₦7,000 | ₦7,000 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 m² | Resource unit | Qty / 1 m² | Unit price | Cost / m² |
|---|---|---|---|---|---|---|
| Moulding/forming/installation labour | Labour | 1 | m² | 1 | ₦13,739 | ₦13,739 |
Equipment and movement
Plant & logistics
Plant, hire, fuel, support equipment and logistics are kept separate so they are not hidden inside the material or labour rate.
| Resource | Type | Qty / 1 m² | Resource unit | Qty / 1 m² | Unit price | Cost / m² |
|---|---|---|---|---|---|---|
| Handling/transport | Logistics | 1 | m² | 1 | ₦1,000 | ₦1,000 |
Personal rate calculator
Change quantities, prices and allowances
Cost additions