Finishes
15 mm cement-sand plaster/render to blockwork
15 mm average cement-sand plaster/render, floated finish, including material wastage and application labour.
Methodology
Resource quantities are normalized from the uploaded residential BOQ and current cement/sand inputs.
Source basis
2-bedroom BOQ material consumption + FMC plaster labour benchmark.
Quantity basis
See exactly what makes up the rate
The rate is analysed for 1 m² of work. Enter the quantity you actually want to execute and every material, labour and plant quantity below will scale without changing the public Charismak reference rate.
What you need to buy
Material quantities
Quantities shown are for one unit of the measured work. The right-hand quantity scales automatically to the work quantity you enter.
| Resource | Type | Qty / 1 m² | Resource unit | Qty / 1 m² | Unit price | Cost / m² |
|---|---|---|---|---|---|---|
| CementSep 2026 Abuja working bulk reference: ₦12,500/50kg bag; editable. | Material | 0.15 | bag | 0.15 | ₦12,500 | ₦1,875 |
| Plaster/sharp sand | Material | 0.035 | m³ | 0.035 | ₦14,400 | ₦504 |
Workmanship
Labour build-up
Labour is shown as the crew, trade, gang-day, day or piecework quantity used to produce one unit of the measured work.
| Resource | Type | Qty / 1 m² | Resource unit | Qty / 1 m² | Unit price | Cost / m² |
|---|---|---|---|---|---|---|
| Plaster/render labour | Labour | 1 | m² | 1 | ₦900 | ₦900 |
Personal rate calculator
Change quantities, prices and allowances
Cost additions